2024-09-30
|
No data
|
COLUMBUS AVENUE, FROM STREET WEST 90 STREET TO STREET WEST 91 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Work not done.Permit expired.
|
2024-09-11
|
No data
|
83 AVENUE, FROM STREET HOOVER AVENUE TO STREET KEW GARDENS ROAD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
New curb.
|
2024-09-02
|
No data
|
99 AVENUE, FROM STREET 213 STREET TO STREET 215 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb installed
|
2024-08-26
|
No data
|
COLUMBUS AVENUE, FROM STREET WEST 90 STREET TO STREET WEST 91 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Workers on site w/ sidewalk flags excavated at this time; in compliance.
|
2024-08-14
|
No data
|
83 AVENUE, FROM STREET HOOVER AVENUE TO STREET KEW GARDENS ROAD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
3 sidewalk flags needs to be fully restored in kind from patch work in front of building #123-30 83 AVENUE
|
2024-06-03
|
No data
|
99 AVENUE, FROM STREET 213 STREET TO STREET 215 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Steel face curb installed on 213 Street b/t 99 Avenue & 102 Avenue. Temp asphalt placed adjacent curb. permit still active.
|
2024-05-20
|
No data
|
WEST 57 STREET, FROM STREET 5 AVENUE TO STREET 6 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No sidewalk occupancy at this time
|
2024-01-05
|
No data
|
INGRAM STREET, FROM STREET 72 AVENUE TO STREET ASCAN AVENUE
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
I OBSERVED THE RESPONDENT HAS STORED A CONSTRUCTION CONTAINER ON THE ROADWAY WITHOUT AN ACTIVE DOT PERMIT I/FO THEIR ACTIVE BUILDING OPERATION (Q00541587-I1-GC EXP. 05/12/2024). RESPONDENT ID THROUGH D.O.B PERMIT ON FILE.
|
2023-12-15
|
No data
|
INGRAM STREET, FROM STREET 72 AVENUE TO STREET ASCAN AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
container incompliance
|
2023-12-07
|
No data
|
INGRAM STREET, FROM STREET 72 AVENUE TO STREET ASCAN AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
container visible
|
2023-11-16
|
No data
|
INGRAM STREET, FROM STREET 72 AVENUE TO STREET ASCAN AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
container incompliance
|
2023-11-14
|
No data
|
INGRAM STREET, FROM STREET 72 AVENUE TO STREET ASCAN AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
container in-compliance
|
2023-01-25
|
No data
|
LAWTON STREET, FROM STREET BROADWAY TO STREET BUSHWICK AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Sidewalk open for pedestrian walkway
|
2022-11-26
|
No data
|
INGRAM STREET, FROM STREET 72 AVENUE TO STREET ASCAN AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
NOV rejected not contractor work. As per google images preexisting work since 2019.
|
2022-11-20
|
No data
|
AINSLIE STREET, FROM STREET GRAHAM AVENUE TO STREET HUMBOLDT STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
New sidewalk flags.
|
2022-11-16
|
No data
|
INGRAM STREET, FROM STREET 72 AVENUE TO STREET ASCAN AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
IFO 72-35 Ingram Street patchwork was done, full flag restoration required
|
2022-09-19
|
No data
|
INGRAM STREET, FROM STREET 72 AVENUE TO STREET ASCAN AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
IFO 72-35 Ingram Street patchwork was done, full flag restoration required
|
2022-09-19
|
No data
|
INGRAM STREET, FROM STREET 72 AVENUE TO STREET ASCAN AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
Condition remains. Patchwork on 1 sidewalk flag. New CAR issued.
|
2022-09-17
|
No data
|
GROSVENOR STREET, FROM STREET EAST DRIVE TO STREET MARINETTE STREET
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
Not Verified. Sidewalk is in compliance at this time. Flags are 5' x 5' when feasible at the driveway at time of inspection.
|
2022-08-08
|
No data
|
GROSVENOR STREET, FROM STREET EAST DRIVE TO STREET MARINETTE STREET
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
sidewalk flags restored in kind
|
2022-07-30
|
No data
|
INGRAM STREET, FROM STREET 72 AVENUE TO STREET ASCAN AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
in front of 72-35 Ingram Street patchwork was done, full flag restoration required
|
2022-04-19
|
No data
|
GROSVENOR STREET, FROM STREET EAST DRIVE TO STREET MARINETTE STREET
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
I observed respondent has failed to correct defective sidewalk flag at 316 Grosvenor Street. 11'10"x4'9" monolithic pour of driveway flag remains. Respondent notified via C.A.R. 20220320081 on 2/11/22, defect has not been corrected.
|
2022-02-15
|
No data
|
69 STREET, FROM STREET CENTRAL AVENUE TO STREET MYRTLE AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk flags installed restored in kind adjacent to property AKA #68-45 MYRTLE AVENUE expansion joints sealed in between the sidewalk, curb & end of the property line in compliance
|
2022-02-11
|
No data
|
GROSVENOR STREET, FROM STREET EAST DRIVE TO STREET MARINETTE STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Driveway flag size 11'11"x4'10". DOT requires flag size 5'x5' where feasible. Large monolithic pour. Replace to proper size.
|
2021-12-31
|
No data
|
38 STREET, FROM STREET 28 AVENUE TO STREET ASTORIA BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk flags restored
|
2021-11-16
|
No data
|
AINSLIE STREET, FROM STREET GRAHAM AVENUE TO STREET HUMBOLDT STREET
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
Sidewalk flags sealed and in compliance.
|
2021-11-03
|
No data
|
38 STREET, FROM STREET 28 AVENUE TO STREET ASTORIA BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk flags restored, expansion joints sealed
|
2021-10-01
|
No data
|
38 STREET, FROM STREET 28 AVENUE TO STREET ASTORIA BOULEVARD
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
curb has been replaced and sealed, free of defects, i.f.o 25-51
|
2021-09-28
|
No data
|
69 STREET, FROM STREET CENTRAL AVENUE TO STREET MYRTLE AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb reveal installed adjacent to property AKA #68-45 MYRTLE AVENUE in compliance
|
2021-09-26
|
No data
|
SHERIDAN AVENUE, FROM STREET EAST 170 STREET TO STREET EAST 171 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk in compliance
|
2021-09-09
|
No data
|
POWER ROAD, FROM STREET 59 AVENUE TO STREET 60 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Concrete sidewalk flags installed at bus shelter opposite 5916.
|
2021-07-06
|
No data
|
38 STREET, FROM STREET 28 AVENUE TO STREET ASTORIA BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb needs to be recessed 1/2" down, in 20' intervals for the placement of sealed expansion joints. Also, curb needs to be free of surface defects and graffiti writing. i/f/o 25-51
|
2021-07-03
|
No data
|
WEST 55 STREET, FROM STREET 11 AVENUE TO STREET 12 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Swk has been restored for building in middle of segment. No obstruction to protected bike lane
|
2021-06-29
|
No data
|
WEST 55 STREET, FROM STREET 11 AVENUE TO STREET 12 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No temp pedwalk.
|
2021-06-05
|
No data
|
115 STREET, FROM STREET 111 AVENUE TO STREET LINDEN BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
no new work found, all new sidewalk work associated with "bioswales"
|
2021-05-27
|
No data
|
5 AVENUE, FROM STREET EAST 57 STREET TO STREET EAST 58 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w repair
|
2021-04-21
|
No data
|
AINSLIE STREET, FROM STREET GRAHAM AVENUE TO STREET HUMBOLDT STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Maintain Fence
|
2021-04-16
|
No data
|
WEST 58 STREET, FROM STREET 5 AVENUE TO STREET GRAND ARMY PLAZA
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
A/T/P/O I found the respondent installed multiple new sidewalk flags with no NYC DOT permit on file. Identified respondent by Permit #M042021090A00 for work in front of 754 5Th Ave which is the same property.
|
2021-04-16
|
No data
|
5 AVENUE, FROM STREET EAST 57 STREET TO STREET EAST 58 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Multiple sidewalk flags have been restored. However expansion joints need to be sealed before permit expires.
|
2021-03-10
|
No data
|
75 ROAD, FROM STREET 162 STREET TO STREET 164 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk installed and sealed.
|
2021-02-22
|
No data
|
AINSLIE STREET, FROM STREET GRAHAM AVENUE TO STREET HUMBOLDT STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
THE SIDEWALK IS CURRENTLY OPEN TO PEDESTRIANS.
|
2021-02-08
|
No data
|
AINSLIE STREET, FROM STREET GRAHAM AVENUE TO STREET HUMBOLDT STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
SIDEWALK IS CURRENTLY NOT BEING OCCUPIED.
|
2020-09-30
|
No data
|
38 STREET, FROM STREET 28 AVENUE TO STREET ASTORIA BOULEVARD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Temp walkway in place.
|
2020-08-26
|
No data
|
CAMBRELENG AVENUE, FROM STREET EAST 189 STREET TO STREET EAST FORDHAM ROAD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w ok
|
2020-06-03
|
No data
|
75 ROAD, FROM STREET 162 STREET TO STREET 164 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Repair sidewalk, expansion joints recessed and sealed.
|
2020-02-28
|
No data
|
69 PLACE, FROM STREET 65 DRIVE TO STREET 69 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk flag restored with expansion joint and sealer
|
2019-10-15
|
No data
|
CAMBRELENG AVENUE, FROM STREET EAST 189 STREET TO STREET EAST FORDHAM ROAD
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
New sidewalk flags sealed.
|
2019-09-29
|
No data
|
KISSENA BOULEVARD, FROM STREET BARCLAY AVENUE TO STREET SANFORD AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Several flags repaired,expansion joints sealed.
|
2019-08-26
|
No data
|
CAMBRELENG AVENUE, FROM STREET EAST 189 STREET TO STREET EAST FORDHAM ROAD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk flag needs plastic caps removed and needs expansion joints properly sealed.
|
2019-05-23
|
No data
|
74 STREET, FROM STREET 41 AVENUE TO STREET BROADWAY
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
new SWK installed, Monolithic curb installed, joints sealed
|
2019-05-23
|
No data
|
BEACH 130 STREET, FROM STREET CRONSTON AVENUE TO STREET NEWPORT AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb
|
2019-02-06
|
No data
|
69 PLACE, FROM STREET 65 DRIVE TO STREET 69 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w restored
|
2018-09-25
|
No data
|
WEST 113 STREET, FROM STREET 7 AVENUE TO STREET 8 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
container on street
|
2018-07-24
|
No data
|
POWER ROAD, FROM STREET 57 AVENUE TO STREET 58 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk restoration completed in compliance with expansion joint seal.
|
2018-05-19
|
No data
|
WEST 167 STREET, FROM STREET AMSTERDAM AVENUE TO STREET AUDUBON AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
sidewalk replaced in compliance
|
2018-04-19
|
No data
|
59 AVENUE, FROM STREET 136 STREET TO STREET LAWRENCE STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
REPLACED PERM SIDEWALK SEALED
|
2018-03-14
|
No data
|
BEACH 130 STREET, FROM STREET CRONSTON AVENUE TO STREET NEWPORT AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
new metal curb installed.
|
2018-02-01
|
No data
|
72 ROAD, FROM STREET 147 STREET TO STREET VLEIGH PLACE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Replaced sidewalk, expansion joints were sealed.
|
2017-12-14
|
No data
|
EAST 34 STREET, FROM STREET 3 AVENUE TO STREET LEXINGTON AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
-No crossing sidewalk work at this time.
|
2017-12-13
|
No data
|
17 STREET, FROM STREET 7 AVENUE TO STREET 8 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
- No refuse container on location at this time.
|
2017-11-16
|
No data
|
EAST 34 STREET, FROM STREET 3 AVENUE TO STREET LEXINGTON AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Sidewalk Crossing, crew working within building property at time of inspection. In compliance with permit stips.Inspector: Matthew Smith
|
2017-11-13
|
No data
|
POWER ROAD, FROM STREET 57 AVENUE TO STREET 58 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
S/W in good condition.
|
2017-10-30
|
No data
|
EAST 34 STREET, FROM STREET 3 AVENUE TO STREET LEXINGTON AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
crew actively removing debris from housing unit at this time
|
2017-10-29
|
No data
|
EAST 34 STREET, FROM STREET 3 AVENUE TO STREET LEXINGTON AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
roadway occupancy adjacent to south curb in-compliance at 160 e 34 st
|
2017-10-11
|
No data
|
WEST 167 STREET, FROM STREET AMSTERDAM AVENUE TO STREET AUDUBON AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Place material on rdwy.
|
2017-09-06
|
No data
|
WEST 167 STREET, FROM STREET AMSTERDAM AVENUE TO STREET AUDUBON AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Place material on rdwy.
|
2017-07-25
|
No data
|
72 ROAD, FROM STREET 147 STREET TO STREET VLEIGH PLACE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk expansion joints sealed
|
2017-05-25
|
No data
|
WEST 167 STREET, FROM STREET AMSTERDAM AVENUE TO STREET AUDUBON AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Material on street
|
2017-05-13
|
No data
|
WEST 167 STREET, FROM STREET AMSTERDAM AVENUE TO STREET AUDUBON AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
MATERIAL ON STREET AT TIME OF INSPECTION
|
2017-04-15
|
No data
|
PETRACCA PLACE, FROM STREET 20 AVENUE TO STREET DEAD END
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w restored
|
2017-04-04
|
No data
|
WEST 167 STREET, FROM STREET AMSTERDAM AVENUE TO STREET AUDUBON AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
material placed on street
|
2017-04-01
|
No data
|
59 AVENUE, FROM STREET 136 STREET TO STREET LAWRENCE STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
new sidewalk installed. expansion joints sealed
|
2017-03-20
|
No data
|
WEST 167 STREET, FROM STREET AMSTERDAM AVENUE TO STREET AUDUBON AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
material
|
2017-03-07
|
No data
|
20 AVENUE, FROM STREET PETRACCA PLACE TO STREET UNNAMED STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w restored
|
2017-03-03
|
No data
|
132 STREET, FROM STREET 15 AVENUE TO STREET 20 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
S/w - expansion joints sealed.
|
2017-01-10
|
No data
|
WEST 167 STREET, FROM STREET AMSTERDAM AVENUE TO STREET AUDUBON AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
material placed on street
|
2017-01-03
|
No data
|
POWER ROAD, FROM STREET 58 AVENUE TO STREET 59 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk flags restored expansion joints sealed, curb repaired.
|
2016-12-27
|
No data
|
WEST 167 STREET, FROM STREET AMSTERDAM AVENUE TO STREET AUDUBON AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Material on the street
|
2016-12-12
|
No data
|
WEST 167 STREET, FROM STREET AMSTERDAM AVENUE TO STREET AUDUBON AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Material on street
|
2016-11-10
|
No data
|
WEST 21 STREET, FROM STREET 8 AVENUE TO STREET 9 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
distinctive s/w acceptable
|
2016-11-06
|
No data
|
FRESH POND ROAD, FROM STREET 59 AVENUE TO STREET FLUSHING AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w flags restored in kind, expansion joints sealed
|
2016-10-23
|
No data
|
FRESH POND ROAD, FROM STREET 59 AVENUE TO STREET FLUSHING AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk repaired expansion joints sealed at time of my inspection
|
2016-10-16
|
No data
|
72 ROAD, FROM STREET 147 STREET TO STREET VLEIGH PLACE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
no work done at time of my inspection
|
2016-09-24
|
No data
|
BEACH 130 STREET, FROM STREET CRONSTON AVENUE TO STREET NEWPORT AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
NEW SIDEWALK FLAGS INSTALLED
|
2016-09-15
|
No data
|
POWER ROAD, FROM STREET 57 AVENUE TO STREET 58 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Perm sidewalk restoration.
|
2016-09-13
|
No data
|
PETRACCA PLACE, FROM STREET 20 AVENUE TO STREET DEAD END
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Multiple sidewalk flags on West side sidewalk restored to grade. All adjacent expansion joints sealed.
|
2016-08-13
|
No data
|
BEACH 130 STREET, FROM STREET CRONSTON AVENUE TO STREET NEWPORT AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
time of inspection, REPLACE SIDEWALK
|
2016-08-09
|
No data
|
57 AVENUE, FROM STREET 98 PLACE TO STREET POWER ROAD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk replaced.
|
2016-07-19
|
No data
|
20 AVENUE, FROM STREET PETRACCA PLACE TO STREET UNNAMED STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sporadic sidewalk flags at North side of block segment ( i/f/o shopping plazas) restored to grade. Adjacent expansion joints sealed.
|
2016-07-17
|
No data
|
20 AVENUE, FROM STREET PETRACCA PLACE TO STREET UNNAMED STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Multiple flags restored on North side sidewalk in block segment. Adjacent expansion joints sealed.
|
2016-07-11
|
No data
|
132 STREET, FROM STREET 15 AVENUE TO STREET 20 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
S/w - expansion joints sealed.
|
2016-06-14
|
No data
|
20 AVENUE, FROM STREET PETRACCA PLACE TO STREET UNNAMED STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Multiple sidewalk flags restored to grade ifo shopping center/complex of BabiesRus/Modell's/Old Navy. Expansion Adjacent expansion joints sealed.
|
2016-05-25
|
No data
|
HORACE HARDING EXPRESSWAY, FROM STREET LIE WESTBOUND ENTRANCE 99 ST TO STREET JUNCTION BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
new sidewalk and curb install in kind
|
2016-04-14
|
No data
|
POWER ROAD, FROM STREET 58 AVENUE TO STREET 59 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk repair joints seal
|
2016-02-28
|
No data
|
POWER ROAD, FROM STREET 57 AVENUE TO STREET 58 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk and curb replace in kind
|
2016-02-04
|
No data
|
KELLY STREET, FROM STREET BEND TO STREET EAST 156 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
permanent cut final
|
2016-01-31
|
No data
|
KELLY STREET, FROM STREET BEND TO STREET EAST 156 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
pass
|
2016-01-22
|
No data
|
57 AVENUE, FROM STREET 98 PLACE TO STREET POWER ROAD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
new sidewalk also sealed
|
2016-01-12
|
No data
|
PETRACCA PLACE, FROM STREET 20 AVENUE TO STREET DEAD END
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
wrong property inspected, car issued in error, all exp joints sealed
|
2016-01-04
|
No data
|
20 AVENUE, FROM STREET PETRACCA PLACE TO STREET UNNAMED STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk flags repaired in kind ifo 139-17. Expansion joints sealed
|
2016-01-03
|
No data
|
KELLY STREET, FROM STREET BEND TO STREET EAST 156 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
perm final
|
2015-12-24
|
No data
|
132 STREET, FROM STREET 15 AVENUE TO STREET 20 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk restored in kind. Expansion Joints sealed
|
2015-12-24
|
No data
|
20 AVENUE, FROM STREET PETRACCA PLACE TO STREET UNNAMED STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk restored in kind. Expansion joints sealed
|
2015-12-22
|
No data
|
PETRACCA PLACE, FROM STREET 20 AVENUE TO STREET DEAD END
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Expansion joints needs to be sealed
|
2015-12-01
|
No data
|
20 AVENUE, FROM STREET PETRACCA PLACE TO STREET UNNAMED STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
ATPO i observed the above respondent failed to comply with stip 013 of NYC DOT permit ,respondent failed to maintain a clear 5 foot sidewalk , closing it off to pedestrian traffic
|
2015-10-26
|
No data
|
163 STREET, FROM STREET 65 AVENUE TO STREET HORACE HARDING EXPRESSWAY
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
container in p/l
|
2015-10-03
|
No data
|
HORACE HARDING EXPRESSWAY, FROM STREET LIE WESTBOUND ENTRANCE 99 ST TO STREET JUNCTION BOULEVARD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Walkway set up / 5' walkway open on sidewalk
|
2015-09-22
|
No data
|
POWER ROAD, FROM STREET 58 AVENUE TO STREET 59 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
new sidewalk installed and sealed
|
2015-08-24
|
No data
|
GRANT AVENUE, FROM STREET ATLANTIC AVENUE TO STREET MC KINLEY AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
container
|
2015-08-18
|
No data
|
POWER ROAD, FROM STREET 57 AVENUE TO STREET 58 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
sidewalk work being done . valid permit broken sidewalk along property line , 5ft walkway
|
2015-06-03
|
No data
|
57 AVENUE, FROM STREET 98 PLACE TO STREET POWER ROAD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
container on roadway
|
2015-06-03
|
No data
|
57 AVENUE, FROM STREET 98 PLACE TO STREET POWER ROAD
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
valid permit for sidewalk repair also walkway in parking lane is provided
|
2015-05-27
|
No data
|
57 AVENUE, FROM STREET 98 PLACE TO STREET POWER ROAD
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
work is under construction
|
2015-05-27
|
No data
|
57 AVENUE, FROM STREET 98 PLACE TO STREET POWER ROAD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
container on roadway
|
2013-12-22
|
No data
|
QUENTIN ROAD, FROM STREET EAST 31 STREET TO STREET EAST 32 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sw
|