2024-06-07
|
No data
|
CARLTON AVENUE, FROM STREET BERGEN STREET TO STREET ST MARKS AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk installed in compliance ifo 576
|
2024-02-19
|
No data
|
BEACH 143 STREET, FROM STREET OCEAN PROMENADE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
no work done
|
2024-02-01
|
No data
|
CARLTON AVENUE, FROM STREET BERGEN STREET TO STREET ST MARKS AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w installed & sealed
|
2024-01-31
|
No data
|
94 STREET, FROM STREET ROCKAWAY BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Completed tangent ramps in the NE3 corner was found to be ADA compliant. Previously measured & collected in Prism on 5/11/21.
|
2024-01-31
|
No data
|
ROCKAWAY BOULEVARD, FROM STREET CROSS BAY BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Completed tangent ramps in the NW2 corner found not to be ADA compliant. Previously measured & collected in Prism on 5/11/21.
|
2023-07-26
|
No data
|
ROCKAWAY BOULEVARD, FROM STREET CROSS BAY BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Completed tangent ramps in the NW2 corner found not to be ADA compliant. Previously measured & collected in Prism on 5/11/21.
|
2023-07-26
|
No data
|
94 STREET, FROM STREET ROCKAWAY BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Completed tangent ramps in the NE3 corner was found to be ADA compliant. Previously measured & collected in Prism on 5/11/21.
|
2023-06-21
|
No data
|
BEACH 127 STREET, FROM STREET OCEAN PROMENADE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Full sidewalk replaced and sealed.
|
2023-06-14
|
No data
|
EAST 7 STREET, FROM STREET 1 AVENUE TO STREET 2 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
- REPAIR SIDEWALK: S/W has been replaced
|
2023-03-20
|
No data
|
BEACH 124 STREET, FROM STREET CRONSTON AVENUE TO STREET NEWPORT AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
PERMITTEEE SUBMITTED NOTORIZED LETTER FROM HOMEOWNER AT 421 B 124 STREET VIA EMAIL ACCEPTING RESPONSIBILITY FOR THE PATCHED FLAG CAUSED BY THIS PERMITTEE TRYING TO INSTALL THE P/L X-JOINT PROPERLY
|
2022-11-17
|
No data
|
182 STREET, FROM STREET 69 AVENUE TO STREET 73 AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
wood form removed.
|
2022-10-18
|
No data
|
88 STREET, FROM STREET 160 AVENUE TO STREET 161 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
full sidewalk replaced and sealed.
|
2022-10-18
|
No data
|
BEACH 124 STREET, FROM STREET CRONSTON AVENUE TO STREET NEWPORT AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Flag at adjacent property damaged during repairs. Flag then patched replace full flag. In driveway saw joints full depth down to roadway and seal.
|
2022-09-06
|
No data
|
88 STREET, FROM STREET 160 AVENUE TO STREET 161 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
OPEN CONSTRUCTION DEBRIS CONTAINER ON STREET, acceptable
|
2022-09-01
|
No data
|
182 STREET, FROM STREET 69 AVENUE TO STREET 73 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Remove wood form between the replaced sidewalk and grass area IFO 69-46
|
2022-09-01
|
No data
|
182 STREET, FROM STREET 69 AVENUE TO STREET 73 AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
Condition remains. Wood form not removed. New CAR issued.
|
2022-08-11
|
No data
|
BEACH 139 STREET, FROM STREET NEWPORT AVENUE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Full sidewalk replaced and sealed.
|
2022-08-11
|
No data
|
BEACH 127 STREET, FROM STREET OCEAN PROMENADE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk replaced and sealed driveway flag slightly larger.
|
2022-08-11
|
No data
|
BEACH 130 STREET, FROM STREET NEWPORT AVENUE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk replaced and sealed.
|
2022-08-05
|
No data
|
LIBERTY AVENUE, FROM STREET 116 STREET TO STREET 117 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Full sidewalk replaced and sealed.
|
2022-05-16
|
No data
|
103 STREET, FROM STREET LIBERTY AVENUE TO STREET ROCKAWAY BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
expansion joints added to curb are recessed and sealed
|
2022-05-12
|
No data
|
BEACH 127 STREET, FROM STREET OCEAN PROMENADE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Sidewalk replaced. Work in progress.
|
2022-05-12
|
No data
|
BEACH 127 STREET, FROM STREET OCEAN PROMENADE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
Condition verified. Container in r/w
|
2022-05-11
|
No data
|
103 STREET, FROM STREET LIBERTY AVENUE TO STREET ROCKAWAY BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Expansion joints not installed in curb sawed down to roadway inspection failed.
|
2022-05-02
|
No data
|
103 STREET, FROM STREET LIBERTY AVENUE TO STREET ROCKAWAY BOULEVARD
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
I observed the respondent failed to install expansion joints in the curb. Thus in violation of section 34RCNY 2-09 (f)(4)(V). A CAR was issued on 1/14.22. CAR #20220320038 the condition remains.
|
2022-04-27
|
No data
|
BEACH 127 STREET, FROM STREET OCEAN PROMENADE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
Complaint verified: There is an open debris container within the parking lane i/f/o 190. Container is in compliance of stipulations within attached permit, as well as Highway rules and regulations for containers. (also addresses SR #: 311-09979407)
|
2022-03-30
|
No data
|
AVENUE J, FROM STREET EAST 23 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Completed tangent ramps in the SE4 corner quadrant are functional and accessible, ramps are non Ada compliant. Previously measured and collected in Prism on 7/7/20.
|
2022-03-08
|
No data
|
182 STREET, FROM STREET 69 AVENUE TO STREET 73 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Remove wooden form from grass area then fill with soil.
|
2022-02-28
|
No data
|
94 STREET, FROM STREET ROCKAWAY BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Newly completed tangent ramps in the NE3 corner found to be ADA compliant. Previously measured & collected in Prism on 5/11/21.
|
2022-02-28
|
No data
|
ROCKAWAY BOULEVARD, FROM STREET 94 STREET TO STREET CROSS BAY BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
No work on sidewalk IFO Model's.
|
2022-02-28
|
No data
|
ROCKAWAY BOULEVARD, FROM STREET CROSS BAY BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Newly completed tangent ramps in the NW2 corner found not to be ADA compliant. Ramps are functional and accessible. Previously measured & collected in Prism on 5/11/21.
|
2022-01-15
|
No data
|
AVENUE J, FROM STREET EAST 23 STREET TO STREET EAST 24 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sw flags installed
|
2022-01-14
|
No data
|
103 STREET, FROM STREET LIBERTY AVENUE TO STREET ROCKAWAY BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb requires expansion joint in driveway area saw down to roadway seal.
|
2021-12-01
|
No data
|
BEACH 135 STREET, FROM STREET NEWPORT AVENUE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk expansion joints recess and sealed
|
2021-11-26
|
No data
|
BEACH 123 STREET, FROM STREET NEWPORT AVENUE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk expansion joints sealed
|
2021-11-03
|
No data
|
5 AVENUE, FROM STREET 147 STREET TO STREET I 678
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb was replaced
|
2021-09-30
|
No data
|
POWER ROAD, FROM STREET 161 AVENUE TO STREET 162 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk flags in compliance at time of inspection
|
2021-09-04
|
No data
|
AVENUE J, FROM STREET EAST 23 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Completed tangent ramps in the SE4 corner quadrant are functional and accessible non Ada compliant. Previously measured and collected in Prism on 7/7/20.
|
2021-08-07
|
No data
|
107 STREET, FROM STREET 107 AVENUE TO STREET 109 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Several flags repaired,expansion joints sealed.
|
2021-07-13
|
No data
|
ROCKAWAY BOULEVARD, FROM STREET CROSS BAY BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Newly completed tangent ramps in the NW2 corner found not to be ADA compliant. Ramps are functional and accessible. Measured & collected in Prism on 5/11/21.
|
2021-07-13
|
No data
|
94 STREET, FROM STREET ROCKAWAY BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Newly completed tangent ramps in the NE3 corner found to be ADA compliant. Measured & collected in Prism on 5/11/21.
|
2021-06-09
|
No data
|
94 STREET, FROM STREET 103 AVENUE TO STREET ROCKAWAY BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk flags restored, expansion joints sealed
|
2021-06-06
|
No data
|
107 STREET, FROM STREET 107 AVENUE TO STREET 109 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk restored
|
2021-05-30
|
No data
|
BEACH 129 STREET, FROM STREET BEACH CHANNEL DRIVE TO STREET CRONSTON AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
No container at this time.
|
2021-05-11
|
No data
|
ROCKAWAY BOULEVARD, FROM STREET CROSS BAY BOULEVARD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Newly completed tangent ramps within the NW2 corner quadrant was found to be non ada compliant, however ramps are functional and accessible. Measured and collected in prism on 5/11/21.
|
2021-05-11
|
No data
|
94 STREET, FROM STREET ROCKAWAY BOULEVARD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Newly completed tangent ramps within the NE3 corner quadrant was found to be ada compliant. Measured and collected in prism on 5/11/21.
|
2020-10-14
|
No data
|
107 STREET, FROM STREET 107 AVENUE TO STREET 109 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
S/w replaced and joints sealed
|
2020-10-06
|
No data
|
BEACH 143 STREET, FROM STREET OCEAN PROMENADE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Multiple s/w flags replaced and sealed, curb replaced and sealed, i/f/o 181
|
2020-10-06
|
No data
|
NEWPORT AVENUE, FROM STREET BEACH 148 STREET TO STREET BEACH 149 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Multiple s/w flags replaced and sealed i/f/o 148-12
|
2020-10-02
|
No data
|
AVENUE J, FROM STREET EAST 23 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Please refer to permit #B042020187A02 for inspection remarks.
|
2020-08-26
|
No data
|
AVENUE J, FROM STREET EAST 23 STREET TO STREET EAST 24 STREET
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
Protest Denied/Repaired. Expansion joints sealed at this time. At time of inspection on 7/28/20 the expansion joint were not sealed which warranted CAR to be issued. permit expired on 7/24/20.
|
2020-08-26
|
No data
|
AVENUE J, FROM STREET EAST 23 STREET TO STREET EAST 24 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Upon arrival at time of inspection respondent BERTOLINI CONTRACTING INC. has sealed the 5 expansion joints in between the sidewalk adjacent to property #2302 on AVENUE J IN COMPLIANCE
|
2020-08-18
|
No data
|
AVENUE W, FROM STREET GERRITSEN AVENUE TO STREET PLUMB 2 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
New curb installed.
|
2020-08-11
|
No data
|
HAVENS PLACE, FROM STREET ATLANTIC AVENUE TO STREET HERKIMER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
CURB INSTALLED
|
2020-08-04
|
No data
|
BEACH 136 STREET, FROM STREET NEWPORT AVENUE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Container in r/w
|
2020-08-01
|
No data
|
AVENUE J, FROM STREET EAST 23 STREET TO STREET EAST 24 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
26 brand new sidewalk flags installed in front of property #2303 on E 23 STREET expansion joints sealed in between the sidewalk & curb in compliance
|
2020-07-28
|
No data
|
AVENUE J, FROM STREET EAST 23 STREET TO STREET EAST 24 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
- Sidewalk expansion joints need to be sealedPlease seal 5 expansion joints in between the sidewalk adjacent to property #2302 on AVENUE J, in a timely fashion. CAR issued
|
2020-07-23
|
No data
|
AVENUE J, FROM STREET EAST 23 STREET TO STREET EAST 24 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Upon arrival respondent BERTOLINI CONTRACTING INC. failed to comply with terms & conditions of stipulation #013, maintain minimum 5 FOOT clear sidewalk passage to all ongoing pedestrians. Nov issued
|
2020-07-15
|
No data
|
AVENUE J, FROM STREET EAST 23 STREET TO STREET EAST 24 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Upon arrival respondent BERTOLINI CONTRACTING INC. failed to comply with terms & conditions of stipulation #013, maintain minimum 5 FOOT clear sidewalk passage to all ongoing pedestrians. Nov issued
|
2020-07-07
|
No data
|
AVENUE J, FROM STREET EAST 23 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Duplicate permit. Please refer to permit #B042020187A02 for inspection remarks.
|
2020-06-26
|
No data
|
AVENUE J, FROM STREET EAST 23 STREET TO STREET EAST 24 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Upon arrival respondent BERTOLINI CONTRACTING INC. failed to maintain the proper street protection under each wheel or roller prior to the delivery of the construction container / equipment stored in the roadway. Nov issued
|
2020-06-23
|
No data
|
AVENUE J, FROM STREET EAST 23 STREET TO STREET EAST 24 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Upon arrival respondent BERTOLINI CONTRACTING INC. failed to maintain the proper street protection under each wheel or roller prior to the delivery of the construction container / equipment stored in the roadway. Nov issued
|
2020-03-01
|
No data
|
HAVENS PLACE, FROM STREET ATLANTIC AVENUE TO STREET HERKIMER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
pass, curb ....
|
2020-02-06
|
No data
|
BEACH 143 STREET, FROM STREET OCEAN PROMENADE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No work done, permit still active.
|
2020-01-12
|
No data
|
5 AVENUE, FROM STREET 147 STREET TO STREET I 678
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
new sidewalk repaired at present time
|
2019-11-01
|
No data
|
ROCKAWAY BEACH BOULEVARD, FROM STREET BEACH 119 STREET TO STREET BEACH 120 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
REPAIR SIDEWALK EXPANSION JOINTS INSTALL
|
2019-09-30
|
No data
|
NEWPORT AVENUE, FROM STREET BEACH 148 STREET TO STREET BEACH 149 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
REPAIR SIDEWALK and seal
|
2019-09-27
|
No data
|
BEACH 143 STREET, FROM STREET OCEAN PROMENADE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
REPAIR SIDEWALK
|
2019-09-06
|
No data
|
82 STREET, FROM STREET 31 AVENUE TO STREET 32 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Repair sidewalk, expansion joints recessed and sealed.
|
2019-07-28
|
No data
|
31 AVENUE, FROM STREET 82 STREET TO STREET 83 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Repair sidewalk , expansion joints recessed and sealed,
|
2019-06-09
|
No data
|
HAVENS PLACE, FROM STREET ATLANTIC AVENUE TO STREET HERKIMER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
swk flags sealed and in compliance
|
2019-04-24
|
No data
|
150 STREET, FROM STREET 94 AVENUE TO STREET 95 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sections of s/w replaced
|
2019-04-24
|
No data
|
AVENUE W, FROM STREET GERRITSEN AVENUE TO STREET PLUMB 2 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
SIDEWALK
|
2019-01-04
|
No data
|
SUTTER AVENUE, FROM STREET 96 STREET TO STREET BEND
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk flags restored expansion joints sealed
|
2018-12-08
|
No data
|
123 STREET, FROM STREET 89 AVENUE TO STREET JAMAICA AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
New Curb Installed
|
2018-10-27
|
No data
|
79 STREET, FROM STREET 156 AVENUE TO STREET 157 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
swk repair
|
2018-10-24
|
No data
|
80 STREET, FROM STREET 149 AVENUE TO STREET 151 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
swk repair
|
2018-10-14
|
No data
|
150 STREET, FROM STREET 94 AVENUE TO STREET 95 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
- REPAIR SIDEWALK
|
2018-06-29
|
No data
|
ECKFORD AVENUE, FROM STREET BEND TO STREET RALEIGH STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb
|
2018-05-10
|
No data
|
AVENUE W, FROM STREET GERRITSEN AVENUE TO STREET PLUMB 2 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w
|
2018-04-13
|
No data
|
80 STREET, FROM STREET 156 AVENUE TO STREET 157 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk repaired
|
2018-04-13
|
No data
|
157 AVENUE, FROM STREET 79 STREET TO STREET 80 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk repaired
|
2018-03-16
|
No data
|
79 STREET, FROM STREET 156 AVENUE TO STREET 157 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
New sidewalk installed at location. Expansion joints sealed.
|
2018-03-04
|
No data
|
ROCKAWAY BEACH BOULEVARD, FROM STREET BEACH 124 STREET TO STREET BEACH 125 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb replaced metal
|
2018-02-16
|
No data
|
79 STREET, FROM STREET 156 AVENUE TO STREET 157 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
NO EQUIPMENT ON R/W
|
2017-12-18
|
No data
|
HAVENS PLACE, FROM STREET ATLANTIC AVENUE TO STREET HERKIMER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w
|
2017-12-02
|
No data
|
78 STREET, FROM STREET 159 AVENUE TO STREET 160 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
RESET, REPAIR OR REPLACE CURB
|
2017-11-29
|
No data
|
HAVENS PLACE, FROM STREET ATLANTIC AVENUE TO STREET HERKIMER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w
|
2017-11-17
|
No data
|
WOODHAVEN BOULEVARD, FROM STREET 92 AVENUE TO STREET 93 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
No new work observed on sidewalk. I/F/O 9217
|
2017-11-14
|
No data
|
JAMAICA AVENUE, FROM STREET 92 STREET TO STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
No work done
|
2017-10-23
|
No data
|
123 STREET, FROM STREET 89 AVENUE TO STREET JAMAICA AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk repaired.
|
2017-10-21
|
No data
|
80 STREET, FROM STREET 149 AVENUE TO STREET 151 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w flags restored, joints sealed
|
2017-10-05
|
No data
|
80 STREET, FROM STREET 156 AVENUE TO STREET 157 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w flags restored, expansion joints sealed
|
2017-09-30
|
No data
|
80 STREET, FROM STREET 156 AVENUE TO STREET 157 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w flags restored, expansion joints sealed
|
2017-09-30
|
No data
|
79 STREET, FROM STREET 156 AVENUE TO STREET 157 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w flags restored, expansion joints sealed
|
2017-09-16
|
No data
|
157 AVENUE, FROM STREET 79 STREET TO STREET 80 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w flags restored, expansion joints sealed at time of inspection
|
2017-09-03
|
No data
|
79 STREET, FROM STREET 156 AVENUE TO STREET 157 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
s/w flags restored, expansion joints sealed
|
2017-06-16
|
No data
|
WARWICK AVENUE, FROM STREET EAST DRIVE TO STREET MARINETTE STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
newly sidwewalk flags installed with expansion joints and sealed
|
2017-01-22
|
No data
|
ECKFORD AVENUE, FROM STREET BEND TO STREET RALEIGH STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
NEW SIDEWALK
|
2016-11-19
|
No data
|
90 STREET, FROM STREET 162 AVENUE TO STREET 163 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk installed and sealed
|
2016-11-02
|
No data
|
84 AVENUE, FROM STREET DANIELS STREET TO STREET SMEDLEY STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk flags restored in kind
|
2016-10-26
|
No data
|
91 STREET, FROM STREET 156 AVENUE TO STREET 157 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
New sidewalk flags and bricks
|
2016-10-05
|
No data
|
ECKFORD AVENUE, FROM STREET BEND TO STREET RALEIGH STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
new curb restored in kind
|
2016-09-17
|
No data
|
POWER ROAD, FROM STREET 100 STREET TO STREET 155 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
restored sidewalk flags with expansion joints and seal
|
2016-08-31
|
No data
|
WARWICK AVENUE, FROM STREET EAST DRIVE TO STREET MARINETTE STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk repaired, joints sealed.
|
2016-07-14
|
No data
|
ECKFORD AVENUE, FROM STREET BEND TO STREET RALEIGH STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk flags restored in kind
|
2016-06-24
|
No data
|
91 STREET, FROM STREET 156 AVENUE TO STREET 157 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk concrete and bricks
|
2016-06-16
|
No data
|
88 STREET, FROM STREET 156 AVENUE TO STREET 157 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
restored sidewalk location in compliance
|
2016-06-15
|
No data
|
123 STREET, FROM STREET 89 AVENUE TO STREET JAMAICA AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk restored in kind, expansion joints sealed
|
2016-05-23
|
No data
|
160 AVENUE, FROM STREET 96 STREET TO STREET 97 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk in compliance expansion joints sealed ifo 96-12
|
2016-05-17
|
No data
|
90 STREET, FROM STREET 162 AVENUE TO STREET 163 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk in compliance expansion joints sealed
|
2016-03-27
|
No data
|
ECKFORD AVENUE, FROM STREET BEND TO STREET RALEIGH STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb replaced in kind
|
2016-02-12
|
No data
|
POWER ROAD, FROM STREET 100 STREET TO STREET 155 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk repaired joints sealed
|
2016-01-15
|
No data
|
101 AVENUE, FROM STREET 103 STREET TO STREET 104 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb and several sidewalk flags restores with expansion joint and seal
|
2016-01-09
|
No data
|
91 STREET, FROM STREET 158 AVENUE TO STREET 159 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
expansion joints installed are sealed
|
2015-12-22
|
No data
|
91 STREET, FROM STREET 156 AVENUE TO STREET 157 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
distinctive s/w expansion joints at curb line
|
2015-12-15
|
No data
|
91 STREET, FROM STREET 158 AVENUE TO STREET 159 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w repaired joints sealed
|
2015-12-09
|
No data
|
156 AVENUE, FROM STREET 90 STREET TO STREET 91 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w repair
|
2015-12-08
|
No data
|
88 STREET, FROM STREET 156 AVENUE TO STREET 157 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
restored sidewalk flags with expansion joint and seal
|
2015-12-06
|
No data
|
ROCKAWAY BEACH BOULEVARD, FROM STREET BEACH 124 STREET TO STREET BEACH 125 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
time of inspection REPAIR SIDEWALK
|
2015-11-08
|
No data
|
160 AVENUE, FROM STREET 96 STREET TO STREET 97 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
expansion joints are sealed
|
2015-11-07
|
No data
|
90 STREET, FROM STREET 162 AVENUE TO STREET 163 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w expansion joints are recessed and sealed
|
2015-09-26
|
No data
|
ECKFORD AVENUE, FROM STREET BEND TO STREET RALEIGH STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
expansion joints sealed
|
2015-09-09
|
No data
|
95 AVENUE, FROM STREET 81 STREET TO STREET 82 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
expansion joints in s/w are now recessed and sealed
|
2015-09-01
|
No data
|
ECKFORD AVENUE, FROM STREET BEND TO STREET RALEIGH STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb replaced in kind
|
2015-08-11
|
No data
|
POWER ROAD, FROM STREET 100 STREET TO STREET 155 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
joints sealed
|
2015-06-30
|
No data
|
101 AVENUE, FROM STREET 103 STREET TO STREET 104 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
flags replaced
|
2015-06-18
|
No data
|
91 STREET, FROM STREET 158 AVENUE TO STREET 159 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
jounts sealed
|
2015-05-22
|
No data
|
91 STREET, FROM STREET 158 AVENUE TO STREET 159 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk repaired ,flag sealed.
|
2015-05-16
|
No data
|
156 AVENUE, FROM STREET 90 STREET TO STREET 91 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
joints sealed
|
2014-12-05
|
No data
|
95 AVENUE, FROM STREET 81 STREET TO STREET 82 STREET
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
THIS CONDITION IS NOT REPAIRED. THE PERMITTEE IS ON A STOP/HOLD FOR FAILURE TO CORRECT DEFECT. AN NOV WAS ISSUED.
|
2014-11-29
|
No data
|
BEACH 136 STREET, FROM STREET CRONSTON AVENUE TO STREET NEWPORT AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
passed
|
2014-11-15
|
No data
|
95 AVENUE, FROM STREET 81 STREET TO STREET 82 STREET
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
failed to seal expansion joints along sidewalk & curb
|
2014-11-02
|
No data
|
156 AVENUE, FROM STREET 90 STREET TO STREET 91 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
repaired sidewalk.
|
2014-10-28
|
No data
|
BEACH 136 STREET, FROM STREET CRONSTON AVENUE TO STREET NEWPORT AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
a/t/p/o, i observed that the above respondent had failed to seal expansion joints. the respindent was notified by car#20144940368 on 9-5-14 to correct the condition but it remains not sealed
|
2014-10-10
|
No data
|
101 AVENUE, FROM STREET 103 STREET TO STREET 104 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Repaired sidewalk.
|
2014-10-08
|
No data
|
95 AVENUE, FROM STREET 81 STREET TO STREET 82 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
- Sidewalk expansion joints need to be sealed
|
2014-09-21
|
No data
|
91 STREET, FROM STREET 158 AVENUE TO STREET 159 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
pass
|
2014-09-05
|
No data
|
BEACH 136 STREET, FROM STREET CRONSTON AVENUE TO STREET NEWPORT AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
please seal joints i/f/o 426
|
2014-04-05
|
No data
|
ROCKAWAY BEACH BOULEVARD, FROM STREET BEACH 111 STREET TO STREET BEACH 112 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb okay
|
2014-01-29
|
No data
|
HARING STREET, FROM STREET AVENUE S TO STREET AVENUE T
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sw
|
2013-10-16
|
No data
|
65 LANE, FROM STREET ADMIRAL AVENUE TO STREET METROPOLITAN AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
repaired s/w flags with expansion joints and seal
|
2013-09-29
|
No data
|
95 STREET, FROM STREET 101 AVENUE TO STREET 103 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Installation of Curb in good condition.
|
2013-09-09
|
No data
|
97 STREET, FROM STREET 164 AVENUE TO STREET 165 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb in good condition.
|
2013-09-07
|
No data
|
164 AVENUE, FROM STREET 96 STREET TO STREET 97 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb in good condition.
|
2013-09-07
|
No data
|
ROCKAWAY BEACH BOULEVARD, FROM STREET BEACH 111 STREET TO STREET BEACH 112 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
work not done
|
2013-07-30
|
No data
|
160 AVENUE, FROM STREET 89 STREET TO STREET 90 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
NEW S/W INSTALLED
|
2013-07-09
|
No data
|
BEACH 149 STREET, FROM STREET NEPONSIT AVENUE TO STREET ROCKAWAY BEACH BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb reset
|
2013-03-21
|
No data
|
95 STREET, FROM STREET 101 AVENUE TO STREET 103 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
new curb
|
2012-12-06
|
No data
|
91 STREET, FROM STREET 159 AVENUE TO STREET 160 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
no new curb @ address reset repaired or / and replace adjacent too
|
2012-10-05
|
No data
|
FILLMORE AVENUE, FROM STREET EAST 35 STREET TO STREET EAST 36 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
No data
|
2012-08-05
|
No data
|
95 STREET, FROM STREET 101 AVENUE TO STREET 103 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
No data
|
2012-05-03
|
No data
|
91 STREET, FROM STREET 159 AVENUE TO STREET 160 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
No data
|
2012-04-27
|
No data
|
97 STREET, FROM STREET 164 AVENUE TO STREET 165 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
PED WALK-OK
|
2012-04-08
|
No data
|
JUNIPER VALLEY ROAD, FROM STREET 75 PLACE TO STREET GRAY STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
No data
|
2012-02-02
|
No data
|
LEFFERTS BOULEVARD, FROM STREET 89 AVENUE TO STREET 91 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk
|
2012-01-07
|
No data
|
97 AVENUE, FROM STREET 91 STREET TO STREET 92 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk
|
2011-08-18
|
No data
|
89 STREET, FROM STREET 86 ROAD TO STREET JAMAICA AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk is final
|
2011-08-05
|
No data
|
91 STREET, FROM STREET 159 AVENUE TO STREET 160 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb
|
2011-05-15
|
No data
|
97 STREET, FROM STREET 164 AVENUE TO STREET 165 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
expansion joints not sealed - permit still valid
|
2011-05-15
|
No data
|
164 AVENUE, FROM STREET 96 STREET TO STREET 97 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
expansion joints not sealed - permit still active
|
2011-05-14
|
No data
|
BEACH 133 STREET, FROM STREET BEACH CHANNEL DRIVE TO STREET CRONSTON AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
No data
|
2011-05-10
|
No data
|
65 LANE, FROM STREET ADMIRAL AVENUE TO STREET METROPOLITAN AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
No data
|
2011-04-08
|
No data
|
65 LANE, FROM STREET ADMIRAL AVENUE TO STREET METROPOLITAN AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No data
|
2010-05-25
|
No data
|
90 STREET, FROM STREET 103 AVENUE TO STREET LIBERTY AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No data
|
2010-01-31
|
No data
|
60 AVENUE, FROM STREET 70 STREET TO STREET 71 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
repaired s/w
|
2009-12-10
|
No data
|
267 STREET, FROM STREET 76 AVENUE TO STREET 77 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk
|
2009-09-26
|
No data
|
102 STREET, FROM STREET 101 AVENUE TO STREET 103 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No data
|
2009-09-26
|
No data
|
101 AVENUE, FROM STREET 97 STREET TO STREET 98 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No data
|
2009-07-18
|
No data
|
95 STREET, FROM STREET 161 AVENUE TO STREET 162 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w repaired
|
2008-10-22
|
No data
|
101 STREET, FROM STREET 95 AVENUE TO STREET 97 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk is final
|