B042024184A20
|
2024-07-02
|
2024-07-26
|
CONSTRUCT NEW SIDEWALK BLG. PAVEMENT
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B012024184F48
|
2024-07-02
|
2024-07-26
|
PAVE STREET-W/ ENGINEERING & INSP FEE-P
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B012024184F47
|
2024-07-02
|
2024-07-26
|
RESET, REPAIR OR REPLACE CURB-PROTECTED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B012024158B17
|
2024-06-06
|
2024-07-05
|
PAVE STREET-W/ ENGINEERING & INSP FEE-P
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B012024158B16
|
2024-06-06
|
2024-07-05
|
RESET, REPAIR OR REPLACE CURB-PROTECTED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B042024158B08
|
2024-06-06
|
2024-07-05
|
CONSTRUCT NEW SIDEWALK BLG. PAVEMENT
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024137A30
|
2024-05-16
|
2024-07-26
|
CROSSING SIDEWALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024137A29
|
2024-05-16
|
2024-07-26
|
PLACE MATERIAL ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024137A36
|
2024-05-16
|
2024-07-26
|
TEMP. CONST. SIGNS/MARKINGS
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024137A35
|
2024-05-16
|
2024-07-26
|
OCCUPANCY OF SIDEWALK AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024137A34
|
2024-05-16
|
2024-07-26
|
PLACE OPEN CONSTRUCTION DEBRIS CONTAINER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024137A33
|
2024-05-16
|
2024-07-26
|
OCCUPANCY OF ROADWAY AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024137A32
|
2024-05-16
|
2024-07-26
|
TEMPORARY PEDESTRIAN WALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024137A31
|
2024-05-16
|
2024-07-26
|
PLACE CONSTRUCTION OFFICE TRAILER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024137A41
|
2024-05-16
|
2024-07-26
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024137A40
|
2024-05-16
|
2024-07-26
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024137A39
|
2024-05-16
|
2024-07-26
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024137A38
|
2024-05-16
|
2024-07-26
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024137A37
|
2024-05-16
|
2024-07-26
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B012024120A17
|
2024-04-29
|
2024-05-22
|
PAVE STREET-W/ ENGINEERING & INSP FEE-P
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B012024120A16
|
2024-04-29
|
2024-05-22
|
RESET, REPAIR OR REPLACE CURB-PROTECTED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B042024120A05
|
2024-04-29
|
2024-05-22
|
CONSTRUCT NEW SIDEWALK BLG. PAVEMENT
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B012024081C37
|
2024-03-21
|
2024-04-16
|
PAVE STREET-W/ ENGINEERING & INSP FEE-P
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B012024081C36
|
2024-03-21
|
2024-04-16
|
RESET, REPAIR OR REPLACE CURB-PROTECTED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B042024081A69
|
2024-03-21
|
2024-04-16
|
CONSTRUCT NEW SIDEWALK BLG. PAVEMENT
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024053B03
|
2024-02-22
|
2024-05-13
|
PLACE CONSTRUCTION OFFICE TRAILER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024053B01
|
2024-02-22
|
2024-05-13
|
PLACE MATERIAL ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024053B13
|
2024-02-22
|
2024-05-13
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024053B12
|
2024-02-22
|
2024-05-13
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024053B11
|
2024-02-22
|
2024-05-13
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024053B10
|
2024-02-22
|
2024-05-13
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024053B09
|
2024-02-22
|
2024-05-13
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024053B08
|
2024-02-22
|
2024-05-13
|
TEMP. CONST. SIGNS/MARKINGS
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024053B07
|
2024-02-22
|
2024-05-13
|
OCCUPANCY OF SIDEWALK AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024053B06
|
2024-02-22
|
2024-05-13
|
PLACE OPEN CONSTRUCTION DEBRIS CONTAINER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024053B05
|
2024-02-22
|
2024-05-13
|
OCCUPANCY OF ROADWAY AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024053B04
|
2024-02-22
|
2024-05-13
|
TEMPORARY PEDESTRIAN WALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024053B02
|
2024-02-22
|
2024-05-13
|
CROSSING SIDEWALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024025C22
|
2024-01-25
|
2024-02-22
|
CROSSING SIDEWALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024025C33
|
2024-01-25
|
2024-02-22
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024025C32
|
2024-01-25
|
2024-02-22
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024025C31
|
2024-01-25
|
2024-02-22
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024025C30
|
2024-01-25
|
2024-02-22
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024025C29
|
2024-01-25
|
2024-02-22
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024025C28
|
2024-01-25
|
2024-02-22
|
TEMP. CONST. SIGNS/MARKINGS
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024025C27
|
2024-01-25
|
2024-02-22
|
OCCUPANCY OF SIDEWALK AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024025C26
|
2024-01-25
|
2024-02-22
|
PLACE OPEN CONSTRUCTION DEBRIS CONTAINER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024025C25
|
2024-01-25
|
2024-02-22
|
OCCUPANCY OF ROADWAY AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024025C24
|
2024-01-25
|
2024-02-22
|
TEMPORARY PEDESTRIAN WALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024025C23
|
2024-01-25
|
2024-02-22
|
PLACE CONSTRUCTION OFFICE TRAILER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022024025C21
|
2024-01-25
|
2024-02-22
|
PLACE MATERIAL ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023356B30
|
2023-12-22
|
2024-01-24
|
CROSSING SIDEWALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023356B29
|
2023-12-22
|
2024-01-24
|
PLACE MATERIAL ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023356B41
|
2023-12-22
|
2024-01-24
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023356B40
|
2023-12-22
|
2024-01-24
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023356B39
|
2023-12-22
|
2024-01-24
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023356B38
|
2023-12-22
|
2024-01-24
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023356B37
|
2023-12-22
|
2024-01-24
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023356B36
|
2023-12-22
|
2024-01-24
|
TEMP. CONST. SIGNS/MARKINGS
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023356B35
|
2023-12-22
|
2024-01-24
|
OCCUPANCY OF SIDEWALK AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023356B34
|
2023-12-22
|
2024-01-24
|
PLACE OPEN CONSTRUCTION DEBRIS CONTAINER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023356B33
|
2023-12-22
|
2024-01-24
|
OCCUPANCY OF ROADWAY AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023356B32
|
2023-12-22
|
2024-01-24
|
TEMPORARY PEDESTRIAN WALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023356B31
|
2023-12-22
|
2024-01-24
|
PLACE CONSTRUCTION OFFICE TRAILER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023333B99
|
2023-11-29
|
2023-12-31
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023333C03
|
2023-11-29
|
2023-12-31
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023333C02
|
2023-11-29
|
2023-12-31
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023333C01
|
2023-11-29
|
2023-12-31
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023333C00
|
2023-11-29
|
2023-12-31
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023333B98
|
2023-11-29
|
2023-12-31
|
TEMP. CONST. SIGNS/MARKINGS
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023333B97
|
2023-11-29
|
2023-12-31
|
OCCUPANCY OF SIDEWALK AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023333B96
|
2023-11-29
|
2023-12-31
|
PLACE OPEN CONSTRUCTION DEBRIS CONTAINER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023333B95
|
2023-11-29
|
2023-12-31
|
OCCUPANCY OF ROADWAY AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023333B94
|
2023-11-29
|
2023-12-31
|
TEMPORARY PEDESTRIAN WALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023333B93
|
2023-11-29
|
2023-12-31
|
PLACE CONSTRUCTION OFFICE TRAILER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023333B92
|
2023-11-29
|
2023-12-31
|
CROSSING SIDEWALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023333B91
|
2023-11-29
|
2023-12-31
|
PLACE MATERIAL ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D23
|
2023-10-18
|
2023-12-03
|
TEMPORARY PEDESTRIAN WALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D22
|
2023-10-18
|
2023-12-03
|
PLACE CONSTRUCTION OFFICE TRAILER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D21
|
2023-10-18
|
2023-12-03
|
CROSSING SIDEWALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D20
|
2023-10-18
|
2023-12-03
|
PLACE MATERIAL ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D34
|
2023-10-18
|
2023-12-03
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D33
|
2023-10-18
|
2023-12-03
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D32
|
2023-10-18
|
2023-12-03
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D31
|
2023-10-18
|
2023-12-03
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D30
|
2023-10-18
|
2023-12-03
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D29
|
2023-10-18
|
2023-12-03
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D28
|
2023-10-18
|
2023-12-03
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D27
|
2023-10-18
|
2023-12-03
|
TEMP. CONST. SIGNS/MARKINGS
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D26
|
2023-10-18
|
2023-12-03
|
OCCUPANCY OF SIDEWALK AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D36
|
2023-10-18
|
2023-12-03
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D35
|
2023-10-18
|
2023-12-03
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D25
|
2023-10-18
|
2023-12-03
|
PLACE OPEN CONSTRUCTION DEBRIS CONTAINER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023291D24
|
2023-10-18
|
2023-12-03
|
OCCUPANCY OF ROADWAY AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023276A61
|
2023-10-03
|
2023-10-30
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023215B13
|
2023-08-03
|
2023-10-30
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023215B11
|
2023-08-03
|
2023-10-30
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023215B10
|
2023-08-03
|
2023-08-10
|
OCCUPANCY OF SIDEWALK AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023215B09
|
2023-08-03
|
2023-08-30
|
OCCUPANCY OF ROADWAY AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023215B12
|
2023-08-03
|
2023-10-30
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023215B14
|
2023-08-03
|
2023-10-30
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B152023207A00
|
2023-07-26
|
2023-08-10
|
DOT USE ONLY-FULL ROADWAY CLOSURE APPL'S
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C29
|
2023-07-24
|
2023-10-30
|
TEMPORARY PEDESTRIAN WALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C26
|
2023-07-24
|
2023-10-30
|
PLACE MATERIAL ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C27
|
2023-07-24
|
2023-10-30
|
CROSSING SIDEWALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C28
|
2023-07-24
|
2023-10-30
|
PLACE CONSTRUCTION OFFICE TRAILER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C30
|
2023-07-24
|
2023-10-30
|
OCCUPANCY OF ROADWAY AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C31
|
2023-07-24
|
2023-10-30
|
PLACE OPEN CONSTRUCTION DEBRIS CONTAINER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C32
|
2023-07-24
|
2023-10-30
|
OCCUPANCY OF SIDEWALK AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C33
|
2023-07-24
|
2023-10-30
|
TEMP. CONST. SIGNS/MARKINGS
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C34
|
2023-07-24
|
2023-10-30
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C35
|
2023-07-24
|
2023-10-30
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C36
|
2023-07-24
|
2023-10-30
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C37
|
2023-07-24
|
2023-10-30
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C38
|
2023-07-24
|
2023-10-30
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C39
|
2023-07-24
|
2023-10-30
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C40
|
2023-07-24
|
2023-10-30
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023205C41
|
2023-07-24
|
2023-10-30
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B012023184D47
|
2023-07-03
|
2023-09-18
|
OPEN PROTECTED SIDEWALK FOR FOUNDATION
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A60
|
2023-04-27
|
2023-08-01
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A59
|
2023-04-27
|
2023-08-01
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A58
|
2023-04-27
|
2023-08-01
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A57
|
2023-04-27
|
2023-08-01
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A56
|
2023-04-27
|
2023-08-01
|
TEMP. CONST. SIGNS/MARKINGS
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A55
|
2023-04-27
|
2023-08-01
|
OCCUPANCY OF SIDEWALK AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A54
|
2023-04-27
|
2023-08-01
|
PLACE OPEN CONSTRUCTION DEBRIS CONTAINER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A53
|
2023-04-27
|
2023-08-01
|
OCCUPANCY OF ROADWAY AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A52
|
2023-04-27
|
2023-08-01
|
TEMPORARY PEDESTRIAN WALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A63
|
2023-04-27
|
2023-08-01
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A50
|
2023-04-27
|
2023-08-01
|
CROSSING SIDEWALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A62
|
2023-04-27
|
2023-08-01
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A61
|
2023-04-27
|
2023-08-01
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A49
|
2023-04-27
|
2023-08-01
|
PLACE MATERIAL ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A64
|
2023-04-27
|
2023-08-01
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023117A51
|
2023-04-27
|
2023-08-01
|
PLACE CONSTRUCTION OFFICE TRAILER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
M042023074A04
|
2023-03-15
|
2023-04-13
|
REPAIR SIDEWALK
|
EAST 24 STREET, MANHATTAN, FROM STREET 3 AVENUE TO STREET LEXINGTON AVENUE
|
B022023031A58
|
2023-01-31
|
2023-05-05
|
CROSSING SIDEWALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A72
|
2023-01-31
|
2023-05-05
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A71
|
2023-01-31
|
2023-05-05
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A70
|
2023-01-31
|
2023-05-05
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A69
|
2023-01-31
|
2023-05-05
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A68
|
2023-01-31
|
2023-05-05
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A67
|
2023-01-31
|
2023-05-05
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A66
|
2023-01-31
|
2023-05-05
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A65
|
2023-01-31
|
2023-05-05
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A64
|
2023-01-31
|
2023-05-05
|
TEMP. CONST. SIGNS/MARKINGS
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A63
|
2023-01-31
|
2023-05-05
|
OCCUPANCY OF SIDEWALK AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A62
|
2023-01-31
|
2023-05-05
|
PLACE OPEN CONSTRUCTION DEBRIS CONTAINER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A61
|
2023-01-31
|
2023-05-05
|
OCCUPANCY OF ROADWAY AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A60
|
2023-01-31
|
2023-05-05
|
TEMPORARY PEDESTRIAN WALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A59
|
2023-01-31
|
2023-05-05
|
PLACE CONSTRUCTION OFFICE TRAILER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022023031A57
|
2023-01-31
|
2023-05-05
|
PLACE MATERIAL ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C47
|
2022-11-28
|
2023-02-04
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C46
|
2022-11-28
|
2023-02-04
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C45
|
2022-11-28
|
2023-02-28
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C44
|
2022-11-28
|
2023-02-04
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C43
|
2022-11-28
|
2023-02-04
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C42
|
2022-11-28
|
2023-02-04
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C41
|
2022-11-28
|
2023-02-04
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C40
|
2022-11-28
|
2023-02-04
|
TEMP. CONST. SIGNS/MARKINGS
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C39
|
2022-11-28
|
2023-02-04
|
OCCUPANCY OF SIDEWALK AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C38
|
2022-11-28
|
2023-02-04
|
PLACE OPEN CONSTRUCTION DEBRIS CONTAINER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C37
|
2022-11-28
|
2023-02-04
|
OCCUPANCY OF ROADWAY AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C36
|
2022-11-28
|
2023-02-04
|
TEMPORARY PEDESTRIAN WALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C35
|
2022-11-28
|
2023-02-04
|
PLACE CONSTRUCTION OFFICE TRAILER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C34
|
2022-11-28
|
2023-02-04
|
CROSSING SIDEWALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C33
|
2022-11-28
|
2023-02-04
|
PLACE MATERIAL ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022332C48
|
2022-11-28
|
2023-02-04
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022325B13
|
2022-11-21
|
2022-12-02
|
CROSSING SIDEWALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022325B25
|
2022-11-21
|
2022-12-02
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022325B24
|
2022-11-21
|
2022-12-02
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022325B23
|
2022-11-21
|
2022-12-02
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022325B22
|
2022-11-21
|
2022-12-02
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022325B21
|
2022-11-21
|
2022-12-02
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022325B20
|
2022-11-21
|
2022-12-02
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022325B19
|
2022-11-21
|
2022-12-02
|
TEMP. CONST. SIGNS/MARKINGS
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022325B18
|
2022-11-21
|
2022-12-02
|
OCCUPANCY OF SIDEWALK AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022325B17
|
2022-11-21
|
2022-12-02
|
PLACE OPEN CONSTRUCTION DEBRIS CONTAINER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022325B16
|
2022-11-21
|
2022-12-02
|
OCCUPANCY OF ROADWAY AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022325B15
|
2022-11-21
|
2022-12-02
|
TEMPORARY PEDESTRIAN WALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022325B14
|
2022-11-21
|
2022-12-02
|
PLACE CONSTRUCTION OFFICE TRAILER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022325B12
|
2022-11-21
|
2022-12-02
|
PLACE MATERIAL ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022255C21
|
2022-09-12
|
2022-12-02
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022255C20
|
2022-09-12
|
2022-12-02
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022238A64
|
2022-08-26
|
2022-11-23
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022238A63
|
2022-08-26
|
2022-11-23
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022238A62
|
2022-08-26
|
2022-11-23
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022238A61
|
2022-08-26
|
2022-11-23
|
TEMP. CONST. SIGNS/MARKINGS
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022238A60
|
2022-08-26
|
2022-11-23
|
OCCUPANCY OF SIDEWALK AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022238A59
|
2022-08-26
|
2022-11-23
|
PLACE OPEN CONSTRUCTION DEBRIS CONTAINER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022238A58
|
2022-08-26
|
2022-11-23
|
OCCUPANCY OF ROADWAY AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022238A57
|
2022-08-26
|
2022-11-23
|
TEMPORARY PEDESTRIAN WALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022238A56
|
2022-08-26
|
2022-11-23
|
PLACE CONSTRUCTION OFFICE TRAILER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022238A55
|
2022-08-26
|
2022-11-23
|
CROSSING SIDEWALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022238A54
|
2022-08-26
|
2022-11-23
|
PLACE MATERIAL ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022238A67
|
2022-08-26
|
2022-11-23
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022238A65
|
2022-08-26
|
2022-11-23
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022238A66
|
2022-08-26
|
2022-11-22
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022192A86
|
2022-07-11
|
2022-09-13
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022172F70
|
2022-06-21
|
2022-09-12
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022132A93
|
2022-05-12
|
2022-08-06
|
PLACE MATERIAL ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022132B06
|
2022-05-12
|
2022-08-06
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022132B05
|
2022-05-12
|
2022-08-06
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B012022132B12
|
2022-05-12
|
2022-06-07
|
INSTALL FENCE - PROTECTED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022132B04
|
2022-05-12
|
2022-08-06
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022132B03
|
2022-05-12
|
2022-08-06
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022132B02
|
2022-05-12
|
2022-08-06
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B012022132B11
|
2022-05-12
|
2022-08-06
|
OPEN PROTECTED SIDEWALK FOR FOUNDATION
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022132B01
|
2022-05-12
|
2022-08-06
|
PLACE EQUIPMENT OTHER THAN CRANE OR SHOV
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022132B00
|
2022-05-12
|
2022-08-06
|
TEMP. CONST. SIGNS/MARKINGS
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022132A99
|
2022-05-12
|
2022-08-06
|
OCCUPANCY OF SIDEWALK AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022132A98
|
2022-05-12
|
2022-08-06
|
PLACE OPEN CONSTRUCTION DEBRIS CONTAINER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022132A97
|
2022-05-12
|
2022-08-06
|
OCCUPANCY OF ROADWAY AS STIPULATED
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022132A96
|
2022-05-12
|
2022-08-06
|
TEMPORARY PEDESTRIAN WALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022132A95
|
2022-05-12
|
2022-08-06
|
PLACE CONSTRUCTION OFFICE TRAILER ON STREET
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|
B022022132A94
|
2022-05-12
|
2022-08-06
|
CROSSING SIDEWALK
|
14 STREET, BROOKLYN, FROM STREET 6 AVENUE TO STREET 7 AVENUE
|