2022-01-14
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
r/w was resurfaced
|
2022-01-14
|
No data
|
RICHMOND TERRACE, FROM STREET PETER P CUSICK WAY TO STREET NORTH RAMP VIADUCT
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
r/w was resurfaced
|
2021-09-11
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w and curb to grade
|
2021-09-11
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w and curb to grade
|
2021-04-25
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
SIDEWALK AND CURB ARE OK
|
2021-04-21
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
SIDEWALK AND CURB OK
|
2021-04-01
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb replaced and s/w replaced
|
2021-04-01
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb replaced
|
2020-08-24
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb replaced
|
2020-08-13
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w and curb replaced
|
2020-06-26
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
roadway resurfaced
|
2020-06-26
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
roadway resurface
|
2020-06-11
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb repaired
|
2020-06-10
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb replaced
|
2020-03-19
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w completed
|
2020-02-05
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
s/w and curb to grade
|
2019-07-01
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
SR# 1-1-1738768541 the roadway was resurfaced after milling took place. Roadway was permanently restored no action taken
|
2019-06-21
|
No data
|
RICHMOND TERRACE, FROM STREET PETER P CUSICK WAY TO STREET NORTH RAMP VIADUCT
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
BPP insp. Roadway milled down 3"inches. rwy awaiting pavement.
|
2019-06-21
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
BPP insp. Roadway milled down 3"inches. rwy awaiting pavement.
|
2019-06-10
|
No data
|
RICHMOND TERRACE, FROM STREET PETER P CUSICK WAY TO STREET NORTH RAMP VIADUCT
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
12'x 11' portion of the roadway waiting to be restored for BPP, portion of roadway not done likely, due to heavy rains
|
2019-06-10
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
There is a 14'x 11' portion of the roadway is down 3". It seems the work is not completed possibly due to rain
|
2019-01-22
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
fence is up blocking entire s/w and curb
|
2019-01-22
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
fence is up blocking entire s/w and curb
|
2018-12-08
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Wooden fence is blocking off worksite for Empire Outlets
|
2018-12-08
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Wooden fence is blocking off worksite for Empire Outlets
|
2018-10-01
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
"Responded to a complaint of delayed traffic, NOT verified at this inspection."
|
2018-09-20
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Cp: "Contr. was at plated site for hydrant relocation one side across to the other."
|
2018-06-26
|
No data
|
NORTH RAMP VIADUCT, FROM STREET BEND TO STREET NYCTA SUBWAY
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
-No visible crane/shovel on location at this time.
|
2018-05-29
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
A/T/P/O I observed the above respondent having damaged NYCDOT equipment.
|
2018-03-11
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Active work site behind fence, Newer active permits taken.
|
2018-02-23
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
r/w occupied
|
2018-02-20
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
s/w closed
|
2018-02-16
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
r/w occupied
|
2018-02-06
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
s/w closed
|
2018-01-31
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
Signs posted to use otherside & flagman on site, while s/w occupancy for truck loading & unloading. Active.
|
2018-01-27
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
r/w occupied
|
2018-01-25
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
no work visible, newer active permit taken.
|
2017-12-17
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb
|
2017-12-17
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
roadway cut
|
2017-11-17
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
A repaired sidewalk/curb.
|
2017-11-17
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
A repaired sidewalk/curb.
|
2017-07-31
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Cp: Revisited plated rw sites based on a shifted plate complaint sent for inspection via email. All plates were counter-sunken with few under grade.
|
2017-07-27
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Cp: Responded to an emailed complaint of man in the hole w/o shoring. NOT VERIFIED on arrival.
|
2017-04-25
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
SPOKE WITH TONY, FROM FRANCIS. ADVISED HIM TO MOVE BARRIERS FROM R/WAY. HE OBLIGED AND MOVED THE BARRIERS. NO ACTION WAS TAKEN.
|
2017-03-27
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Steel pins were raised above the grade of the roadway which needs to be hammered down to secure the countersunk plates. Spoke to Forman, Chris, advising to address the condition. Insp. was based on complaint # 1-1-1384811683..
|
2017-03-15
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Heavy snow/ice on the ground. Permitted equipment in place. Supervisor Peter D' Agostino at (917)939-4191.
|
2017-03-06
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Spoke with the Forman on location, Chris, in regard to countersunk steel plates still deflecting making noise and advised that plates need to be better secured. Email to be sent to SI Base as per Boro Comm. complaint.
|
2017-03-03
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
A/t/p/o I observed the above respondent failed to secure their steel plate to the roadway. Above respondent steel was deflecting 2" in the driving lane and not secure to the roadway.
|
2017-03-01
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Cp: Inspected Ferry construction site based on Borough Commissioner's complaint for delayed traffic during crane activity.
|
2017-03-01
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Cp: Inspected Ferry construction site based on Borough Commissioner's complaint for delayed traffic during crane activity.
|
2017-02-28
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
On site supervisor, John from FRANCIS SITE DEVELOPMENT CO., LLC was issued a warning to bring 2 sets of steel plates up to grade which were 2-3 inches below grade. Crew was working behind property line at this time due to 9pm stips.
|
2017-02-22
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
FRANCIS SITE DEVELOPMENT CO., LLC- was re-setting the plates when inspection was previously conducted (2/22/17 @ 12:35) . No further action taken.
|
2017-02-22
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Special from SI BASE: Contractor was re-setting the plates. Spoke with the person in charge, John, and was informed that theyâll be here for about 20 more minutes.
|
2017-02-09
|
No data
|
RICHMOND TERRACE, FROM STREET NORTH RAMP VIADUCT TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Steel plates in center Driving lane going to segments, 1 is shifted off IFO 36 Richmond Terr. Issued NICA to additional S012017027A33
|
2017-02-09
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
SHIFTED PLATE WAS RESET.
|
2017-02-09
|
No data
|
RICHMOND TERRACE, FROM STREET FERRY TERMINAL DRIVE TO STREET SCHUYLER STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Email complaint from Central Dispatch: Shifted Steel Plate IFO 36 Richmond Terr btw Wall St and Schuyler St- exposing excavation along Driving lane. Call made for 3hr noticeD05
|