2024-09-11
|
No data
|
137 STREET, FROM STREET 31 ROAD TO STREET 32 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Roadway Occupied At Time Of Inspection
|
2024-09-01
|
No data
|
23 AVENUE, FROM STREET 146 STREET TO STREET LEE COURT
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
No BPP Paving work done at location.
|
2024-08-06
|
No data
|
23 AVENUE, FROM STREET 146 STREET TO STREET LEE COURT
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
New concrete curb installed at location.
|
2024-06-05
|
No data
|
74 STREET, FROM STREET 43 AVENUE TO STREET WOODSIDE AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Concrete curb restored in front of 42-16.
|
2024-05-30
|
No data
|
37 AVENUE, FROM STREET 138 STREET TO STREET MAIN STREET
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
The respondent was observed closing the sidewalk with a construction fence without obtaining a DOT permit to do so. Respondent was identified by DOB permit# 440645063-01-EW-OT for doing interior and exterior renovation to building at location.
|
2024-05-16
|
No data
|
137 STREET, FROM STREET 31 ROAD TO STREET 32 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Sidewalk in compliance
|
2024-05-08
|
No data
|
74 STREET, FROM STREET 43 AVENUE TO STREET WOODSIDE AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
BPP completed, Curb to curb 29’, Milled Area is 20’, Depth is 3”, in front of 42-16.
|
2024-04-26
|
No data
|
37 AVENUE, FROM STREET 138 STREET TO STREET MAIN STREET
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
I observed the above respondent construction fence closing off 54' X 9’ portion of sidewalk without a valid DOT permit on file to do so in front of 136-21 37 Avenue. The respondent was ID by D.O.B. permit # 440645063-01-EW-OT
|
2024-04-23
|
No data
|
NORTH 9 STREET, FROM STREET KENT AVENUE TO STREET WYTHE AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Width of Roadway: 29ft 9inWidth of milled area: 20ft 6inLength of milled area: 35ft 6in Depth of milled area: 3in down
|
2024-03-19
|
No data
|
37 AVENUE, FROM STREET 138 STREET TO STREET MAIN STREET
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
I observed the above respondent construction fence closing off 54' X 9’ portion of sidewalk without a valid DOT permit on file to do so in front of 136-21 37 Avenue.
|
2024-03-08
|
No data
|
137 STREET, FROM STREET 31 ROAD TO STREET 32 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
A/T/P/O I observed the above respondent having permitted temporary construction signs without the 5 digit permittee number posted on the signs. The respondent was identified by their permit # Q022024031B63.
|
2024-02-15
|
No data
|
137 STREET, FROM STREET 31 ROAD TO STREET 32 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No Sidewalk Crossing Being Done On Site At Time Of Inspection
|
2024-02-02
|
No data
|
217 STREET, FROM STREET 40 AVENUE TO STREET DEAD END
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
BPP perm restoration
|
2023-12-26
|
No data
|
WEEKS LANE, FROM STREET 50 AVENUE TO STREET 51 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sidewalk restored in kind
|
2023-12-07
|
No data
|
DAHLGREN PLACE, FROM STREET GOE EASTBOUND EXIT 17 TO STREET FT HILL PLACE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb repaired in front of 205 Dahlgren Place.
|
2023-11-22
|
No data
|
19 AVENUE, FROM STREET 149 STREET TO STREET 150 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
CURB REPLACED
|
2023-11-16
|
No data
|
MANHATTAN AVENUE, FROM STREET AINSLIE STREET TO STREET DEVOE STREET
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
Materials stored on the roadway and sidewalk without a permit.
|
2023-11-13
|
No data
|
217 STREET, FROM STREET 40 AVENUE TO STREET DEAD END
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
New sidewalk in place I/F/O 40-20 new home.
|
2023-10-08
|
No data
|
23 AVENUE, FROM STREET 146 STREET TO STREET LEE COURT
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No BPP paving roadway work started at this time of inspection.
|
2023-09-19
|
No data
|
DAHLGREN PLACE, FROM STREET GOE EASTBOUND EXIT 17 TO STREET FT HILL PLACE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
New curb installed in compliance
|
2023-08-07
|
No data
|
23 AVENUE, FROM STREET 146 STREET TO STREET LEE COURT
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Curb restored at this time. Active permit on file.
|
2023-06-23
|
No data
|
19 AVENUE, FROM STREET 149 STREET TO STREET 150 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
50’x20’ bpp has been paved at time of inspection
|
2023-06-15
|
No data
|
21 AVENUE, FROM STREET 154 STREET TO STREET MURRAY STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
BPP restoration
|
2023-06-03
|
No data
|
217 STREET, FROM STREET 40 AVENUE TO STREET DEAD END
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
B.P.P. milling in compliance within the roadway in front of 40-20 217th Street: Curb to Curb: 29'6" / Milled Area: 40'x20'6" / Depth:3" / 1/2+5' milled: YES / Waiver: NO
|
2023-05-23
|
No data
|
CORONA AVENUE, FROM STREET 48 AVENUE TO STREET 88 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
BPP paving done in front of 88-14.
|
2023-03-10
|
No data
|
58 AVENUE, FROM STREET 230 STREET TO STREET EASTHAMPTON BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
BPP to grade
|
2022-12-06
|
No data
|
43 STREET, FROM STREET 30 AVENUE TO STREET 31 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
New sidewalk squares in front of 30-71.
|
2022-12-04
|
No data
|
44 STREET, FROM STREET 43 AVENUE TO STREET SKILLMAN AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Steel face curb installed in front of 41-26.
|
2022-10-27
|
No data
|
15 STREET, FROM STREET 3 AVENUE TO STREET 4 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Sunken area was permanently restored to grade, pass.
|
2022-10-27
|
No data
|
15 STREET, FROM STREET 3 AVENUE TO STREET 4 AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
Protest Denied/ Repaired. Sunken location repaired within BPP.
|
2022-09-29
|
No data
|
15 STREET, FROM STREET 3 AVENUE TO STREET 4 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
(2ft. x 1ft.) area within a BPP permanent restoration was sunken down 4 inches. The area was then temporarily restored to grade. Please permanently restore the area to grade.In front of 139 15 Street between 3 Avenue and 4 Avenue.
|
2022-09-29
|
No data
|
15 STREET, FROM STREET 3 AVENUE TO STREET 4 AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
I observed the above respondent failed to respond to NICA #20228020137 issued on 9/28/2022 at 5:01PM. Respondent failed to repair a permanent BPP restoration that is sunken down 4 inches below the roadway. ID by cited permit.
|
2022-09-28
|
No data
|
15 STREET, FROM STREET 3 AVENUE TO STREET 4 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
4” depth cave-in located in BPP roadway restoration, IFO #139
|
2022-09-28
|
No data
|
15 STREET, FROM STREET 3 AVENUE TO STREET 4 AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
Permanent restoration in the roadway with localized area sunken 3 inches. NICA re-inspection failed.
|
2022-07-12
|
No data
|
146 STREET, FROM STREET 32 AVENUE TO STREET 33 AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
BPP resealed.
|
2022-06-10
|
No data
|
15 STREET, FROM STREET 3 AVENUE TO STREET 4 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No work done.
|
2022-06-07
|
No data
|
41 AVENUE, FROM STREET 210 STREET TO STREET 211 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
sidewalk restored in compliance
|
2022-05-31
|
No data
|
15 STREET, FROM STREET 3 AVENUE TO STREET 4 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb (Concrete) found to be in compliance
|
2022-04-05
|
No data
|
CORONA AVENUE, FROM STREET 48 AVENUE TO STREET 88 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Length of the milled roadway property line to property line: 32’Width of the entire roadway curb to curb: 44’Width of the milled roadway: 27’Depth of the milled roadway: 3”No wavier obtained as per foreman on site ANTHONY
|
2022-03-18
|
No data
|
62 DRIVE, FROM STREET 84 PLACE TO STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Steel faced curb installed
|
2022-03-14
|
No data
|
146 STREET, FROM STREET 32 AVENUE TO STREET 33 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Concrete curb installed if/o 32-11.
|
2022-03-08
|
No data
|
WOODHAVEN BOULEVARD, FROM STREET 62 DRIVE TO STREET 63 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Steel faced curb installed
|
2022-03-08
|
No data
|
63 AVENUE, FROM STREET 84 PLACE TO STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Steel faced curb installed
|
2022-01-25
|
No data
|
78 STREET, FROM STREET 17 AVENUE TO STREET 18 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb has been replaced and acceptable
|
2022-01-13
|
No data
|
58 AVENUE, FROM STREET 203 STREET TO STREET CLEARVIEW EXPRESSWAY
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
New curb installed
|
2022-01-06
|
No data
|
58 AVENUE, FROM STREET 230 STREET TO STREET EASTHAMPTON BOULEVARD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
BPP competed and acceptable. • Curb to Curb width – 30’• Milled area – 20’• Depth of milled area – 3’’
|
2021-12-23
|
No data
|
55 STREET, FROM STREET 9 AVENUE TO STREET FT HAMILTON PARKWAY
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Temporary construction signs posted
|
2021-12-23
|
No data
|
CORONA AVENUE, FROM STREET 48 AVENUE TO STREET 88 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Steel faced curb restored in kind in front of 8814.
|
2021-12-22
|
No data
|
50 AVENUE, FROM STREET 196 PLACE TO STREET 196 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb replaced.
|
2021-12-22
|
No data
|
196 PLACE, FROM STREET 49 AVENUE TO STREET 50 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb replaced.
|
2021-12-07
|
No data
|
CORONA AVENUE, FROM STREET 48 AVENUE TO STREET 88 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No work started. No work done. No inspection found at this time.
|
2021-11-16
|
No data
|
37 AVENUE, FROM STREET 138 STREET TO STREET MAIN STREET
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
Respondent closed the sidewalk with a construction fence without obtaining a DOT permit to do so. Respondent was identified by DOB permit# 440645063-01-EW-OT pulled for interior and exterior renovation work to building at location.
|
2021-11-12
|
No data
|
55 STREET, FROM STREET 9 AVENUE TO STREET FT HAMILTON PARKWAY
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
No boom truck found at this construction site.
|
2021-09-07
|
No data
|
37 AVENUE, FROM STREET 138 STREET TO STREET MAIN STREET
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
Respondent closed the sidewalk with a construction fence without obtaining a DOT permit to do so. Respondent was identified by DOB permit# 440645063-01-EW-OT for doing interior and exterior renovation to building at location.
|
2021-07-18
|
No data
|
146 STREET, FROM STREET 32 AVENUE TO STREET 33 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
CAR - to reseal all three sides of new building BPP paving.
|
2021-06-09
|
No data
|
78 STREET, FROM STREET 17 AVENUE TO STREET 18 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb installed along with sidewalk flags.
|
2021-05-22
|
No data
|
50 AVENUE, FROM STREET 196 PLACE TO STREET 196 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
curb in compliance at time of inspection
|
2021-05-03
|
No data
|
58 AVENUE, FROM STREET 230 STREET TO STREET EASTHAMPTON BOULEVARD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Roadway is clear i/f/o 230-01 58 Avenue
|
2021-04-08
|
No data
|
63 AVENUE, FROM STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
Condition repaired. Permittee obtained permit #Q042020363A18 for the newly completed tangent ramps in the NW corner. Ramps are functional and accessible.
|
2020-12-08
|
No data
|
62 DRIVE, FROM STREET 84 PLACE TO STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
BPP done in roadway.
|
2020-12-08
|
No data
|
WOODHAVEN BOULEVARD, FROM STREET 62 DRIVE TO STREET 63 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
BPP done then Con edison cut into location.
|
2020-11-12
|
No data
|
63 AVENUE, FROM STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
Permittee failed to obtain a 410 permit for the newly completed tangent ramps in the NW2 corner. Previously measured and collected on 7/18/19.
|
2020-09-11
|
No data
|
63 AVENUE, FROM STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
Permittee failed to obtain a 410 permit for the newly completed tangent ramps in the NW2 corner. Previously measured and collected on 7/18/19.
|
2020-07-28
|
No data
|
146 STREET, FROM STREET 32 AVENUE TO STREET 33 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
concrete curb was installed
|
2020-05-08
|
No data
|
63 AVENUE, FROM STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
Newly completed tangent ramps in the NW2 corner found not to be ADA compliant. Ramps are functional, accessible measured and collected on 7/18/19.
|
2020-05-08
|
No data
|
63 AVENUE, FROM STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
Curb reveal has been rectified by the 1/2+5 pavement install, however permittee failed to obtain the correct 410 ped ramp intersection permit. Will pass this one out and reissue another CAR.
|
2020-01-14
|
No data
|
WOODHAVEN BOULEVARD, FROM STREET 62 DRIVE TO STREET 63 AVENUE
|
No data
|
Street Construction Inspections: Complaint
|
Department of Transportation
|
ARTZ DOT 429133-F5K8 compliant not verified: There are 3 catch basin drains in front of and on side of building. New sidewalk and steel faced curb installed.
|
2019-12-31
|
No data
|
78 STREET, FROM STREET 17 AVENUE TO STREET 18 AVENUE
|
No data
|
Street Construction Inspections: NOV Re-Inspect
|
Department of Transportation
|
Sidewalk still not sealed, CAR#20194510947 was written
|
2019-11-30
|
No data
|
78 STREET, FROM STREET 17 AVENUE TO STREET 18 AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
CLOSE
|
2019-11-14
|
No data
|
196 PLACE, FROM STREET 49 AVENUE TO STREET 50 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb installation completed in compliance with expansion joint seal. (Side of 196-15 50 Ave.)
|
2019-10-29
|
No data
|
EAST 61 STREET, FROM STREET LEXINGTON AVENUE TO STREET PARK AVENUE
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
expansion joints have been sealed
|
2019-10-16
|
No data
|
78 STREET, FROM STREET 17 AVENUE TO STREET 18 AVENUE
|
No data
|
Street Construction Inspections: NOV Re-Inspect
|
Department of Transportation
|
I observed the above respondent has a temporary restoration on the roadway adjacent to a newly installed curb. Respondent failed to permanently restore roadway within required time, permit expired on 5/29/2019. Cited permit used for ID.
|
2019-10-16
|
No data
|
78 STREET, FROM STREET 17 AVENUE TO STREET 18 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Seal expansion joints in between new curb and sidewalk flags.In front of 1715 78 Street between 17 Avenue and 18 Avenue.
|
2019-09-22
|
No data
|
WOODHAVEN BOULEVARD, FROM STREET 62 DRIVE TO STREET 63 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Steel faced curb 4" above maximum height required. Elderly people will have difficulties navigating the curb. In addition, there are barricades, cones and wooden slabs and beams remaining on the sidewalk.
|
2019-09-14
|
No data
|
78 STREET, FROM STREET 17 AVENUE TO STREET 18 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
ATPO I observed a temporary restoration on the roadway by the newly installed curb. Respondent failed to permanently restore its temporary roadway restoration. Cited permit used for identification.
|
2019-09-14
|
No data
|
78 STREET, FROM STREET 17 AVENUE TO STREET 18 AVENUE
|
No data
|
Street Construction Inspections: NOV Re-Inspect
|
Department of Transportation
|
Homeowner permit secured B042018124A15
|
2019-09-12
|
No data
|
EAST 61 STREET, FROM STREET LEXINGTON AVENUE TO STREET PARK AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
I/F/O 134 seal expansion joints
|
2019-09-07
|
No data
|
WOODHAVEN BOULEVARD, FROM STREET 62 DRIVE TO STREET 63 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
The above respondent failed to notice nyc dot hiqa brough office within 4 hour prey to paving. As per stipulation 1/2 + 5.
|
2019-09-07
|
No data
|
63 AVENUE, FROM STREET 84 PLACE TO STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Refer to permit #Q012019220E08 on file , NOV issued on 9/7/2019 Failure to comply with terms and conditions of DOT permit.
|
2019-08-28
|
No data
|
63 AVENUE, FROM STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
No 410 permit on file. Newly completed tangent ramps in the NW2 corner found not to be ADA compliant. Ramps are functional, accessible measured and collected on 7/18/19. Updated 8/28/19. (This is the 2nd CAR)
|
2019-08-28
|
No data
|
63 AVENUE, FROM STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: CAR Re-Inspect
|
Department of Transportation
|
Permittee failed to obtain a 410 permit. We’ll pass this one out and reissue another CAR.
|
2019-08-20
|
No data
|
62 DRIVE, FROM STREET 84 PLACE TO STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
136'4"x 27' of wearing course replaced on the BBP.
|
2019-08-19
|
No data
|
62 DRIVE, FROM STREET 84 PLACE TO STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Steel faced curb replaced, joints sealed. On the Woodhaven Blvd. side of property, curb is unusually high, 10-14 inches.
|
2019-08-11
|
No data
|
WOODHAVEN BOULEVARD, FROM STREET 62 DRIVE TO STREET 63 AVENUE
|
No data
|
Street Construction Inspections: NOV Re-Inspect
|
Department of Transportation
|
construct new sidewalk work is completed and finalized. no one on site.
|
2019-08-10
|
No data
|
63 AVENUE, FROM STREET 84 PLACE TO STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: NOV Re-Inspect
|
Department of Transportation
|
sidewalk construction work completed and finalized under permit number Q042019129A65
|
2019-07-18
|
No data
|
63 AVENUE, FROM STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
Completed tangent ramps measured and collected on 7/18/19 however ramp1 is non Ada compliant.
|
2019-07-05
|
No data
|
63 AVENUE, FROM STREET 84 PLACE TO STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
NB - work in progress - 32 linear feet curb opened - permit expired,NOV issued to the GC.
|
2019-07-02
|
No data
|
50 AVENUE, FROM STREET 196 PLACE TO STREET 196 STREET
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
Curb repaired
|
2019-06-25
|
No data
|
WOODHAVEN BOULEVARD, FROM STREET 62 DRIVE TO STREET 63 AVENUE
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
I Observed the above respondent excavated 180' X 15' width of the sidewalk in front of 62-96 Woodhaven Blvd to construct new sidewalk without an active NYCDOT permit on file. Above permit #Q042019129A64 expired on 6/11/2019 was used for ID purpose.
|
2019-06-25
|
No data
|
63 AVENUE, FROM STREET 84 PLACE TO STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Failure to comply with terms and conditions of DOT permit stip ID 078.
|
2019-06-25
|
No data
|
63 AVENUE, FROM STREET 84 PLACE TO STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
Bobcat skid-steer loader stored on the sidewalk without a NYCDOT storage of equipment permit on file, at 62-96 Woodhaven Blvd on 63 Ave. Respondent was ID by their sidewalk construction permit #Q042019129A65, that expired on 6/11/2019.
|
2019-06-25
|
No data
|
63 AVENUE, FROM STREET 84 PLACE TO STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Post-Audit
|
Department of Transportation
|
100' X 10' width of the sidewalk excavated to construct new sidewalk at 62-96 Woodhaven Blvd on 63 Ave, without an active NYCDOT permit on file. Above permit #Q042019129A65 expired on 6/11/2019 was used for ID purppose.
|
2019-06-25
|
No data
|
WOODHAVEN BOULEVARD, FROM STREET 62 DRIVE TO STREET 63 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
Failure to comply with terms and conditions of DOT permit stip ID #078.
|
2019-06-25
|
No data
|
WOODHAVEN BOULEVARD, FROM STREET 62 DRIVE TO STREET 63 AVENUE
|
No data
|
Street Construction Inspections: Pick-Up
|
Department of Transportation
|
Mini Excavator stored on the sidewalk in front of 62-96 Woodhaven Blvd, without a NYCDOT permit on file to store equipment on street. Respondent was ID by their sidewalk construction permit Q042019129A64 that expired on 6/11/2019.
|
2019-06-11
|
No data
|
WOODHAVEN BOULEVARD, FROM STREET 62 DRIVE TO STREET 63 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
i spoke to supervisor work will be completed in the future
|
2019-06-11
|
No data
|
196 PLACE, FROM STREET 49 AVENUE TO STREET 50 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
I OBSERVED THE RESPONDENT VIOLATED STIPULATION (1/2+5') AND IS REQUIRED TO CALL THE NYC DOT HIQA BOROUGH OFFICE WITHIN 4 HOURS PRIOR TO PAVING.ROADWAY PAVED I/F/O 196-15 50 AVENUE ON 196 PLACE. DOT HIQA NEVER NOTIFIED.
|
2019-06-11
|
No data
|
50 AVENUE, FROM STREET 196 PLACE TO STREET 196 STREET
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
I OBSERVED THE RESPONDENT VIOLATED STIPULATION (1/2+5') AND IS REQUIRED TO CALL THE NYC DOT HIQA BOROUGH OFFICE WITHIN 4 HOURS PRIOR TO PAVING.ROADWAY PAVED I/F/O 196-15 50 AVENUE. DOT HIQA NEVER NOTIFIED.
|
2019-06-11
|
No data
|
62 DRIVE, FROM STREET 84 PLACE TO STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
no work done
|
2019-06-11
|
No data
|
63 AVENUE, FROM STREET 84 PLACE TO STREET WOODHAVEN BOULEVARD
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
no work start
|
2019-05-11
|
No data
|
78 STREET, FROM STREET 17 AVENUE TO STREET 18 AVENUE
|
No data
|
Street Construction Inspections: Active
|
Department of Transportation
|
A/T/P/O I observed the Respondent had Repaired Several Sidewalk Flags without a Valid Permit During Installation Of Curb. Permit was only Installation of Curb Only.Also, Sidewalk Flags are not Uniformed as Per DOT Rules & Regulations.
|